Change Order Template

By BRIX Editorial Team · Updated

A change order template is a one-page form for changing a signed contract's scope, price or schedule. It identifies the original contract, the reason for the change, exactly what work is added or removed, the price of the change, the new contract total, the effect on the completion date and payments, and signatures from both sides before the work starts.

Key takeaways

  • The full form is below, plus a printable version you can fill in and save as a PDF.
  • Get it signed before the changed work starts. A verbal "go ahead" is the most common way contractors end up doing extra work for free.
  • Always show the running contract total: original price, prior change orders, this change, new total.
  • This is a starting point, not legal advice. Some states set specific change order rules for home improvement work.

The free change order template

Copy the form or download the printable version. Fill one out every time the scope changes, number them in order (CO #1, #2, #3) and keep the signed copies with the job file.

CHANGE ORDER

Contract

Change order #: ____ Date: ________

Contractor: ____________________ License #: ________

Owner: ____________________ Project address: ____________________

Original contract date: ________ Job / contract #: ________

Reason for change (check one)

☐ Owner request ☐ Hidden or unforeseen condition ☐ Code or inspector requirement ☐ Design change ☐ Other: ________

Description of change

Work added, removed or changed (location, materials, quantities): ______________________________

Price of change

Labor: ___ hrs × $___ = $_____

Materials: $_____

Equipment / subcontractor: $_____

Other (disposal, permit): $_____

This change order: + / − $_____

Contract total

Original contract price: $_____

Previous change orders (net): $_____

This change order: $_____

New contract total: $_____

Schedule and payment

Schedule impact: + / − ___ working days. New completion date: ________

Payment for this change: due with next progress payment / on completion / before work starts

Agreement

This change order becomes part of the contract named above. All other terms stay the same. The work described here will not begin until both parties sign.

Owner: ____________________ Printed name: ____________ Date: ________

Contractor: ____________________ Printed name: ____________ Date: ________

What does a change order need to include?

A change order needs to tie back to the original contract, describe the change precisely, price it, show the new contract total, state the schedule and payment impact, and carry both signatures. Leave any of those out and you've written a note, not an amendment the customer agreed to. For the full background on pricing and tracking, see what is a change order.

Change order fields and why they matter
FieldWhy it's there
Change order numberSequential numbers make it easy to see if one is missing and to reference it on the invoice.
Original contract referenceShows this amends a specific signed contract, not a separate deal.
Reason for changeOwner requests, hidden conditions and inspector calls are priced and argued differently. Record which one it was.
DescriptionSpecific enough that someone who wasn't there could check the work was done: what, where, how many.
Price breakdownLabor, materials and other costs shown separately make the number easier to accept.
Running contract totalPrevents final-invoice surprises. The customer signs off on the new total every time.
Schedule impactIf the change adds days, say so now. Otherwise you own the delay.
Payment timingSmall changes can ride on the next progress payment; big material orders may need payment upfront.
Signatures before workThe whole point. Unsigned change orders are the main source of unpaid extra work.

Filled example: rotten subfloor found during a bathroom remodel

A remodeler pulls the old toilet and vanity and finds the subfloor soft and rotted from a long-running leak. Here's the change order they write before laying the new tile. Prices are illustrative.

Change order #2, hall bath remodel
ItemDetailAmount
ReasonHidden condition: water-damaged subfloor under toilet and vanity, found during demo
DescriptionRemove and replace approx. 24 sq ft of subfloor with 3/4" plywood; sister two damaged joists; treat area
Labor6 hrs × $95$570.00
MaterialsPlywood, joist lumber, adhesive, fasteners, treatment$260.00
DisposalRotted material haul-off$45.00
This change order+$875.00
Original contract priceSigned March 3$18,400.00
Previous change ordersCO #1, upgraded exhaust fan+$650.00
New contract total$19,925.00
Schedule impact+2 working days; completion moves from April 11 to April 15
PaymentAdded to the next progress payment
Illustrative prices. Photos of the rotted subfloor were attached to the change order and texted to the owner before signing.

How do change orders differ by trade?

Common change orders by trade
TradeTypical changesWhat to note on the form
Remodeling / GCOwner upgrades, hidden rot or framing issues, layout changesAllowance overages and selection changes separately from hidden conditions
RoofingExtra decking beyond the allowance, extra layers, added flashing or ventsSheet count and per-sheet price that match the original estimate
ElectricalInspector-required upgrades, added circuits or fixtures, panel capacity issuesInspection reference and which code item triggered the change
PlumbingCorroded lines found behind walls, relocated fixtures, code-required valvesAccess and wall repair responsibility
HVACDuct modifications, electrical upgrades, line set replacementWhether the change affects equipment sizing or warranty registration
Landscaping / hardscapeAdded square footage, rock or poor soil found when digging, drainageQuantities in yards, square feet or linear feet
PaintingExtra drywall repair, added rooms, color changes after work startsNumber of coats and surfaces affected

Common change order mistakes

  • Doing the work first. Even a text saying "go ahead" is weak proof. Get a signature (paper or electronic) first.
  • Pricing at bare cost. A change order should carry your normal overhead and profit, plus a little for the disruption.
  • No running total. Customers who see the total climb one signed step at a time don't get shocked by the final invoice.
  • Vague descriptions. "Extra electrical work: $1,200" invites a dispute. Say what, where and how many.
  • Ignoring schedule impact. If you don't add days on the form, a late finish can become your problem.
  • Not carrying it to the invoice. List each approved change order on your invoice and in your job costing so revenue and costs match.

Frequently asked questions

Does a change order have to be signed by both parties?

It should be. A change order signed by both the owner and the contractor is clear proof the customer agreed to the new scope and price. Some states require signatures for home improvement change orders, so check your state's rules.

Can a change order be done by text or email?

Electronic signatures are generally valid under federal and state e-signature laws, so an emailed form signed electronically can work. A plain text reply saying "OK" is weaker proof. Send the full form with the price and new total, and get a signature on it.

Who pays for hidden conditions found during a job?

Usually whatever your contract says. Many residential contracts say hidden conditions, such as rot behind a wall, will be priced as a change order. That's why the estimate template includes a hidden-conditions clause. Without one, expect a harder conversation.

Can a change order reduce the contract price?

Yes. A deductive change order removes work and lowers the price, for example when an owner decides to supply their own fixtures. Use the same form, mark the amount as a credit and update the running total.

What's the difference between a change order and a change directive?

A change order is agreed and signed by both sides, including the price. A change directive, used mostly on commercial and public contracts, orders the contractor to proceed before the price is agreed, with the cost settled later under the contract's terms.

How should I price a change order?

Price it like the original job: labor, materials, equipment and subcontractors, plus your overhead and profit. Our change order guide shows the formula, and the job pricing calculator can help you check the number.

Sources

  1. California Business and Professions Code § 7159.6 (extra work and change orders) (checked October 12, 2026)
  2. CSLB, Contracting for Success (home improvement contract requirements) (checked October 12, 2026)

Written by BRIX Editorial Team. Published October 19, 2026. Last updated October 19, 2026.

How we research and update pages: editorial policy.

Let BRIX run the phones and the books.
You run the work.

BRIX answers every call, follows up every lead, sends the quotes and invoices, and keeps QuickBooks tax-ready.

Call now(518) 588-1122Text